is the person responsible for the business value of the project and for deciding what work to do and in what order when using a

Scrum method
Business
1 answer:
Romashka-Z-Leto [24]3 years ago
4 0

Answer:

product owner

Explanation:

The Scrum method is a framework for developing, delivering, and sustaining complex products in many fields of including research, sales, marketing and advanced technologies as seen below. In this methodology, the individual responsible for the business value of the project and for deciding what work to do is the product owner. This individual is usually the project's key stakeholder which gives him the responsibility of providing the vision of what the product should ultimately be to the rest of the team..

You might be interested in
During March, the production department of a process operations system completed and transferred to finished goods 23,000 units
Alchen [17]

Answer:

c. $1.58.

Explanation:

The computation of the direct materials cost per equivalent unit is given below:

Equivalent units for material is

= 100% of 193,000 + 100% of 28,000

= 193,000 + 28,000

= 221,000

Equivalent cost for material is

= $94,100 + $254,800

= $348,900

So, the direct materials cost per equivalent unit is

= $348,900 ÷ 221,000

= $1.58

4 0
2 years ago
Conducting research about an occupation, company, or job can increase your employability. Please select the best answer from the
UkoKoshka [18]
Your answer will be true! good luck
7 0
3 years ago
Read 2 more answers
It is said that kone is embedding intelligence across its supply chain and enables smarter buildings. explain.
alexandr402 [8]

KONE started the next stage of its strategy, Sustainable success with consumers, in January 2021. With innovative intelligent solutions, we will increase the value we provide for clients during the four-year strategy term and further integrate sustainability into all of our activities.

Core goods and services: through connectivity and adaptability, they meet the unique demands of each client for a seamless experience. All goods and services shall be made as cost-effective and environmentally friendly as possible.

In order to provide customers with value in new ways, new customer value solutions are being developed and integrated with existing core products and services.

Smart and sustainable cities: become the go-to partner for the construction of smart and sustainable cities.

In this extremely fragmented and fast-growing economy, the service industry in China is becoming the undisputed market leader.

Core values and concepts form the foundation of our culture. We never err on the side of our core values. They consist of sustainability, quality, and safety. The core of our culture is comprised of our values, which stand for the attitudes and actions that KONE wants to encourage.

To learn more about Kone from the given link.

brainly.com/question/27007848

#SPJ4

8 0
1 year ago
Rogen Corporation manufactures a single product. The standard cost per unit of product is shown below.
OleMash [197]

Answer:

1. Material cost variance                            $

Standard material cost ($6  x  4,300)  25,800

Less: Actual ,aterial cost                       27,900

Material cost variance                            2,100(A)

2. Material price variance

= (Standard price - Actual price) x Actual quantity purchased

= ($6 - $6.20) x 4,500 pounds

= $900( A)

Actual price

=  Actual material cost/Actual quantity purchased

Actual price

= $27,900/4,500 pounds = $6.20

3. Material usage variance

= (Standard quantity - Actual quantity used) x Standard price

= (1 x 4,300 - 4,500) x $6

= $1,200(A)

4. Labour cost variance:                           $

Standard labour cost ($18.30 x 4,300)   78,690

Less: Actual labour cost                          77,500

Labour cost variance                                1,190

5. Labour rate variance

=(Standard rate - Actual rate) x Actual hours worked

= ($12.20 - $12.40) x 6,250 hours

= $1,250(A)

6. Labour efficiency variance

= (Standard hours - actual hours worked) x Standard rate

= (1.50 hours x 4,300 - 6,250) x $12.20

= $2,440(F)

Actual rate = Actual labour cost/Actual hours worked

Actual rate = $77,500/6,250 hours

Actual rate = $12.40

= (SR - AR) x Actual hour worked

7. Total overhead variance                                  $

 Standard overhead cost ($24 x 4,300)          103,200

Less: Actual overhead cost(78,430+ 26,670)  105,100

Total overhead variance                                     1,900

Less: Actual overhead cost

Explanation:

Material cost variance is the difference between standard material cost and actual material cost.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                

Material price variance is the difference between standard price and actual price multiplied by actual quantity purchased.

Material usage variance is the difference between standard quantity and actual quantity used multiplied by standard price.

Labour cost variance is the difference between standard labour cost and actual labour cost.

Labour rate variance is the difference between standard rate and actual rate multiplied by actual hours worked.

Labour efficiency variance is the difference between standard hours and actual hours worked multiplied by standard rate.

Total overhead variance is the difference between standard total overhead cost and actual total overhead cost.

7 0
3 years ago
When a buyer is represented by a licensee, who is responsible for following up on issues identified in the inspection report to
s344n2d4d5 [400]

The buyer's agent  is responsible for following up on issues identified in the inspection report to ensure that they are addressed.

<h3>What is a buyer's agent called?</h3>

Long story short: a buyer's agent can technically be called the “selling agent,” once a contract has been entered into.

A listing agent is referred to as the “seller's agent,” since they are representing the seller.

<h3>What is the difference between agent and buyer?</h3>

A seller real estate agent will work only for the seller and have only the seller's interest at heart.

A buyer's broker will work only for the buyer and have only the buyer's interest at heart.

Learn more about buyer's agent here:

<h3>brainly.com/question/15026765</h3><h3 /><h3>#SPJ4</h3>
8 0
1 year ago
Other questions:
  • What is the maker movement? (A) Systems used to create the digital designs and then manufacture the products.(B) Serialization o
    5·1 answer
  • The pension plan was amended last year, creating a prior service cost of $20 million. Service cost and interest cost for the yea
    7·1 answer
  • Brittany started a law practice as a sole proprietor. She owned a computer, printer, desk, and file cabinet she purchased during
    15·1 answer
  • Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginnin
    10·1 answer
  • Which of the following is one of the seven website design elements that marketers can use to produce an effective customer exper
    7·1 answer
  • 5-5 TIME TO REACH A FINANCIAL GOAL You have $33,556.25 in a brokerage account, and you
    14·1 answer
  • The income statement of Pharoah Company is shown below.
    8·1 answer
  • In a(n) ________ strategy, managers try to gain a competitive advantage by focusing the energy of all the organization's departm
    8·1 answer
  • Question 14 of 20
    5·1 answer
  • in the cost approach to valuation, land value can be estimated by comparing sales of vacant land that are similar to the subject
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!