Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Answer:
$25
Explanation:
We can calculate intrinsic value by intrinsic formula
Formula : intrinsic Value = (purchased price- current price) x 100
intrinsic Value = (45-44.75) x 100
intrinsic Value = $25
Is that the question or what i need info.XD
Answer:
b. Used to estimate how fast prices will double using a given annual inflation rate
Explanation:
Rule of 72 is a fast statistical method to determine how long an investment will double given annual interest rate.
Simply divide 72 by the annual interest rate.
Alternatively it can be used to calculated annual rate of return required to double investment.
Alternatively it can be used to calculate annual rate of return required to double an investment.
For example if $1,000 is to be doubled in 5 years.
Years to double= 72/ Interest
Interest= 72/5= 14.4%