Answer: 12.88%
Explanation:
The following information can.be inferred from the question:
Purchase price of share = $36.48
Dividend = $1.62
Selling price = $41.18
Capital gain = $41.18 - $36.48 = $4.70
Capital gain yield:
= Capital gain / Purchase price × 100
= (4.70 / 36.48) × 100
= 0.1288
= 12.88%
Answer:
(A) I, II, and IV only
Explanation:
The Material Requirements Planning MRP is used to calculate tha materials needed for production. It may be done by software but it can be done without any technological tool.
The most important information for MRP is about the available inventory for future production, in this way the company will know what materials are needed for future production. To provide the materials on time it is necessary to know the master schedules of production, making sure that the supplies will be ready on time for manufacturing process. Finally, the accurate Bills of materials are used as a check list to verify that there is not any pending component for the production process. Even when the MRP may include costs, it is not a vital component for the system and some companies can have MRP without including costs.
These dashboards help teams keep track of the progress and success of company-wide metrics and enable management to make data-driven decisions on future business goals. Management dashboards may include graphs, images, tables, numeric data, and data from case studies, or a combination of these elements.
Answer:
1. $590
2. $9.83
Explanation:
1.
Total Number of Direct Labor Hours:
= Total Labor Cost ÷ Labor Rate Per Hour
= 150 ÷ 15
= 10 Hours
Total Overheads:
= Total Number of Direct Labor Hours*Predetermined Overhead Rate
= 10 × 21
= 210
Total Manufacturing Cost = 230 + 150 + 210
= $590
2.
Average Cost:
= Total Manufacturing Cost ÷ Number of Units
= 590 ÷ 60
= $9.83
What do you mean as 'Not like McDonald's'? Do you mean fast food or what?