Answer:
Predetermined overhead rate=$19.5/machine hour
The company applied $877500 to the units produced.
Explanation:
a) Pre-determined overhead rate= <u>Budgeted overhead manufacturing cost</u>
Estimated number of machine hours
=975000/50000=$19.5/machine hour.
b)Applied overhead = Pre-determined overhead rate * Actual machine hours
= 19.5 * 45000
=$877500.
c.
In traditional costing we use as base for calculating overhead rate is machine hours or labor hours but in activity based costing we identify activity that consume resources,identify cost driver of each activity,compute cost rate per cost driver unit and finally assign cost to products by multiplying cost driver rate.
Predetermined overhead rate= estimated overhead/Estimated base (cost driver).
Answer:
It is cheaper to make the part. In three years the company will save $12,000.
Explanation:
Giving the following information:
Units= 40,000
Variable costs= $1.60 per unit
Fixed costs= $40,000 per year
Gilberto is considering buying the part from a supplier for a quoted price of $2.70 per unit guaranteed for three years.
We need to calculate the total cost of making and buying the part.
Make in-house:
Total cost= 1.6*40,000 + 40,000= $104,000
Buy:
Total cost= 40,000*2.7= $108,000
It is cheaper to make the part. In three years the company will save $12,000.
Answer:
The present value of the contract is 0.5% higher if the rent is paid at the beginning of the month. That is equal to $11.28 for every $100 of rent.
Explanation:
if the rent is paid at the beginning of the month, the present value of the lease contract will be:
PV = monthly rent x PV annuity due factor
we are not given the monthly rent, but we know the PV annuity due factor for 0.5% and 24 periods = 22.67568
if the rent is paid at the end of the month, the PV = monthly rent x PV ordinary annuity factor
the PV ordinary annuity factor, 0.5%, 24 periods = 22.56287
assuming that the rent is $100 (just to calculate a %), the PV of an annuity due = $2,267.57
the PV of an ordinary annuity = $2,256.29
the difference between them = [($2,267.57 / $2,256.29) - 1] x 100 = 0.5%
Answer:
The correct answer is:
Expenditures—2017 in the amount of $200. (C.)
Explanation:
This scenario describes a record that was less than the actual amount spent on the General Fund supplies. The amount recorded was $2,000, meanwhile the actual amount spent was $2,000. This entails that an amount worth $200 was not recorded, hence it will be debited as expenditures, but the question now is where the debit will be recorded?
This review was done in January 2017, meaning that the income statement for the 2016 Fiscal year must have been balanced, hence the amount will be an expenditure recorded in 2017, but the particulars will have a description that it was a carried over expenditure from 2016. Therefore $200 will be debited from 2017 as expenditures.
Based on the CPI in both places, the Brexington salary in Charlieville is $30,000.
<h3>Brexington salary in Charlieville </h3>
This can be found by the formula:
= Brexington salary x CPI of Charlieville / CPI of Brexington
Solving gives
= 50,000 x (90 / 150)
= $30,000
In conclusion, option A is correct.
Find out more on CPI at brainly.com/question/512131.