Answer:
Early tasks opposed to later tasks.
Explanation:
Shortening is a strategic procedure used by project managers to reduce or shorten a project's duration by cutting the duration of critical path tasks.
The rationale behind shortening of a project is basically to have a competitive advantage or edge in the market. In order to compete successfully, project managers are always expected to be spontaneous in bringing their company's goods and services to the market in a flash.
There are two important ways of shortening a particular project, these are;
1. Crashing.
2. Task splitting.
In project management, the longest task is considered to be the most effective and efficient candidate activities to shorten a project's duration.
In general, the better candidates for shortening are early tasks opposed to later tasks. The early start of tasks represents one of the primary date used in project scheduling and it's the earliest date a project manager commences an activity, with respect to all its predecessors and successors.
Early tasks usually involves the use of an easy approach to project kickoff while later tasks uses the difficult approach.
Answer:
There are some indirect social costs that are included in marginal cost of firms. such as climate change due to green house gas emission, pollution, systemic risk (risk that banking system takes). These costs impose negative effect on economy and are not directly borne by consumer or producer.
There are some indirect social gains that are not included in price paid for good, such as driving an electric vehicle, improved education, fire proof homes, construction and operations of public goods like parks, street lights. These benefits impose positive effect on economy and are n directly borne by consumer or producer.
Answer:
Break-even point in total units= 951.7units
Explanation:
<em>Break-even point is the level of activity at which a firm must operate such that its total revenue will equal its total costs. At this point, the company makes no profit or loss</em>.
It is calculated using this formula:
<em>Break-even point (in units) = Fixed cost/ average contribution per unit</em>
<em> Blue Plaid</em>
Contribution per unit 43-30 = 13 52-45 = 7
<em>Average contribution per unit </em>
= ( (13× 4) + (7×5) )/9
= $ 9.66 per unit
<em>Break-even point in total units</em>
= $9200/$ 9.66
= 951.7units
Break-even point in total units= 951.7units
Duration of the project. from start to end