Answer: finish to finish
Explanation:
A lag is minimum amount of time that is required for a dependent activity have to be delayed to either start or end.
If testing cannot be completed any earlier than four days after the prototype has been built, the type of lag that exists is finish to finish.
Answer:
Decrease logistics support requirements.
Explanation:
Decrease logistics support requirements is the correct answer because the increase in reliability decreases the requirement to correct the commodity or equipment. Therefore, the logistic support decreases which further decreases the manpower waste. Additionally, the good reliability shows that the product's quality is good and it will work efficiently for a longer time period. Thus, a good quality product requires less logistic support.
Answer:
It will be demanded more or used more because as we advance in technology more people will start to use these new electronics so many people with get their eyesight ruined by the constant blue light their eyes are receiving which will lead to people getting laser eye surgery to fix their damaged eyes.
Explanation:
A job may just be temporary a career normally is for a lifetime and is specific field that you work in for example law, engineering,etc
Answer:
All of the above.
Explanation:
Job analysis is when manager uses information available as a criteria for determining attributes required to perform a job.
In job analysis, information is made available to managers to know which employee is best suited for a particular role. It is also used to measure the capacity of employees whether they are being under or over utilized.
For effective job redistribution, job analysis is best recommended because it describes the work of current employee, working conditions and necessary educational certifications. Skills needed to perform on a role are also part of what is being considered in job analysis.