Answer:
The answer is "Option d".
Explanation:
The Iteration Management is also an activity in which all members of the team will determine how many the backlog team will allocate towards the next Iteration, and each team wraps up the work only as a group of determined iteration targets. in the given question the "choice d" is correct because The plans to achieve without training entered PO or design staff and requirements have not even been identified, and the wrong choice can be defined as follows:
- In choice A, T' he PO doesn't give the story detail, that's why it's incorrect.
- In choice B, the doesn't a team left the past for more refining with the PO in the Project Backlog, that's why it's incorrect.
- In choice C, The Development Team has not found some other team dependency, that's why it's incorrect.
Answer:
the answer is true. it is a high level language
Answer: NOR or XNOR gate
Explanation:
In NOR gate we get a high value of the output only when its input has a low value. i.e. for 0 and 0 we get a value of 1.
In XNOR gate which is the compliment of the OR gate we get the output as 1 when all the inputs are 0.
Answer:
5/ 18
Explanation:
Given :
List A: [20,10,20]
List B: [40,10,30,20,40,30]
Chance that number drawn from list A is larger than or equal to that drawn dlfrom list B.
If:
A = 20
B ≤ 20 : [10,20] = 2
A = 10
B ≤ 10 : [10] = 1
A = 20
B ≤ 20 : [10,20] = 2
Probability = Required outcome / Total possible outcomes
Hence,
required outcome = (2 + 2 +1) = 5
Total possible outcomes = 3C1 * 6C1 = (3 * 6) = 18
Hence,
chance that the number we drew from list A is larger than or equal to the number we drew from list B
= 5 / 18