Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
When you estimate, you round each number, the add.
We round them to
700+620, which is 1320
So our non estimated answer is 1323
But our estimated answer is 1320
Answer:
The other zeros are -2 and 3.
Step-by-step explanation:
As 1 is a zero then (x - 1) is a factor so we divide:
x - 1 )x^3-2x^2-5x+6(x^2-x-6
x^3-x^2
-x^2-5x
-x^2+x
-6x+6
-6x+6
...........
x^2 - x - 6 = 0
(x - 3)(x + 2)
x = -2, 3.