Let x represent the original production time. Then 70x is the order quantity involved.
When the same order quantity is produced at a rate of 80 items per day for x-5 days, we have the equation ...
70x = 80(x -5)
70x = 80x -400
0 = 10x -400 . . . . . subtract 70x
0 = x -40 . . . . . . . . divide by 10
40 = x . . . . . . . . . . add 40
The original schedule was for production to take 40 days.