Answer: No
Explanation:
When computing a project analysis for a project, only relevant cash flow should be included in the Project's cash flow analysis. Relevant cash-flow are those that will only occur if the project was embarked on.
If the cash flow in question is still going to occur even if the project wasn't initiated as is the case with Project A, it is not a relevant cash-flow and should not be included in the cash-flow analysis.