Answer:
(a). 72.9%.
(b). 13.6 hr.
Step-by-step explanation:
So, we are given the following data or parameters or information which is going to assist us in solving this question/problem;
=> "A welder produces 7 welded assemblies during the first day on a new job, and the seventh assembly takes 45 minutes (unit time). "
=> The worker produces 10 welded assemblies on the second day, and the 10th assembly on the second day takes 30 minutes"
So, we will be making use of the Crawford learning curve model.
T(7) + 10 = T (17) = 30 min.
T(7) = T1(7)^b = 45.
T(17 ) = T1(17)^b = 30.
(T1) = 45/7^b = 30/17^b.
45/30 = 7^b/17^b = (7/17)^b.
1.5 = (0.41177)^b.
ln 1.5 = b ln 0.41177.
0.40547 = -0.8873 b.
b = - 0.45696.
=> 2^ -0.45696 = 0.7285.
= 72.9%.
(b). T1= 45/7^ - 045696 = 109.5 hr.
V(TT)(17) = 109.5 {(17.51^ - 0.45696 – 0.51^ - 0.45696) / (1 - 0.45696)} .
V(TT) (17) = 109.5 {(4.7317 - 0.6863) / 0.54304} .
= 815.7 min .
= 13.595 hr.
Answer:
1. No, Joe is not correct
2. 
Step-by-step explanation:
Given: b and c are parallel lines
To find:
1. whether the given statement is correct or not
2. 
Solution:
1.
Sum of two angles that form a linear pair is equal to 
(linear pair)

So, Joe is not correct
2.
If two lines are parallel then alternate interior angles are equal.
As b and c are parallel lines,
(alternate interior angles)
12 centimeters is greater
Hope this helps! :D
Answer:
3x + 9 + 4x + x = 8x + 9
Step-by-step explanation:
combine like terms
Let the length of the patio is x and width is 3/4x
So according to the equation x.3/4x = 432
x^2. 3/4 =432
x^2 =432 times 4/3
x^2 =1728/3 =576
x= 24
The length is 24 ft