6

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation

of the critical path is:
A. 3.
B. 5.
C. 9.
D. 16.
E. 25.
Business
1 answer:
KonstantinChe [14]3 years ago
6 0

Answer:

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is:

C. 9.

Explanation:

The implication is that the standard deviation of the critical path is the sum of the standard deviations of the four activities on the critical path.  This sums to 9 days (1 + 2 + 4 + 2), implying that the critical path varies from the mean days of critical path activities by 9 days plus or minus.

You might be interested in
Amberjack Company is trying to decide on an allocation base to use to assign manufacturing overhead to jobs. The company has alw
HACTEHA [7]

Answer:

Pooooop

Explanation:

3 0
3 years ago
How do u feel about colorado’s position
pickupchik [31]
On what you have to be more espesific
4 0
3 years ago
A firm’s income statement included the following data. The firm’s average tax rate was 20%. Cost of goods sold $ 9,000 Income ta
Semmy [17]

Answer:

a. $12,000

b. $32,000

c. $17,000

Explanation:

The computations are shown below:

a.  Net income = (Income tax paid ÷ Tax rate) – Income tax paid    

Net income = ($3,000 ÷  20%) - $3,000    

                   = $12,000

b.  Revenues = Cost of goods sold + Income tax paid + Administration expense + Interest paid + Depreciation + Net income

= $9,000 + $3,000 + $4,000 + $2,000 + $2,000 + $12,000

= $32,000

3. EBIT = Net income + Interest expense + Taxes

= $12,000 + $2,000 + $3,000

= $17,000

8 0
3 years ago
What helps a consumer determine the quantity of something to buy?
Molodets [167]

Answer:

marginal benefit

Explanation:

consumers are most likely going to buy something with value

3 0
3 years ago
Read 2 more answers
4. How might living under anarchy be desirable, compared to other forms of government with more power? How might it be bad? (4 p
Zepler [3.9K]
Anarchy is good and bad. Compared to communism it is WAY BETTER. Though, you can't vote on your leader like in democracies. Especially if you agree with the leader's values in an anarchy you would probably enjoy it. Also anarchies do have lots of power. I would say to search this up on google though.
6 0
3 years ago
Other questions:
  • Crystal is teaching a newly promoted supervisor how to use the company’s performance management system. The supervisor asks Crys
    8·1 answer
  • The company president does not believe that the formula should be altered for fear it will tarnish the company's brand
    12·1 answer
  • What is the purpose of using two different techniques to determine the densities of these two metals?
    12·1 answer
  • Consider the following situations for Shocker: a. On November 28, 2018, Shocker receives a $2,700 payment from a customer for se
    7·1 answer
  • ___________ is the ability of a product to satisfy a customer. A. Economic utility B. Value C. Purchasing power D. Outsourcing
    5·1 answer
  • A(n) _____ is central to individuals and organizations of all sizes and ensures that information can be shared across all busine
    13·1 answer
  • At its date of incorporation, Sauder, Inc. issued 100,000 shares of its $10 par common stock at $11 per share. During the curren
    5·1 answer
  • Solve for x and y,when 2x+y-5=0 and 3x-2y-18=0​
    14·1 answer
  • Which is the most important decision factor in transportation?
    9·1 answer
  • Other things equal, an improvement in productivity will a. shift the aggregate demand curve to the left. b. shift the aggregate
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!