<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.
We are given that the insect can lift 1.182 x 10^3 times
it's own weight. Say that w is weight, so the lift is:
lift = 1.182 x 10^3 * w
Assuming that your body weight is 60 kg, therefore you
can lift:
lift = 1.182 x 10^3 * 60 kg = 70,920 kg
Answer:
-30x^2-9x+12 all real numbers
Step-by-step explanation:
f(x) = -6x + 3 and g(x) = 5x + 4
f(x) * g(x) = (-6x + 3) * ( 5x + 4)
FOIL
= -30x^2 -24x+15x +12
Combine like terms
=-30x^2-9x+12
The domain is what numbers x can take
There are no restrictions so all real numbers