Answer:
Check the explanation
Explanation:
A vending machine controller is that type of machine that comes with a single serial port on the same chip as the programmable processor. The controller comprises of a port arbitrator that selectively attaches or links one of a number of serially communicating devices to this single serial port.
Kindly check the attached image to get the step by step explanation to the above question.
Answer:
The maximum power that can be generated is 127.788 kW
Explanation:
Using the steam table
Enthalpy at 20 bar = 2799 kJ/kg
Enthalpy at 2 bar = 2707 kJ/kg
Change in enthalpy = 2799 - 2707 = 92 kJ/kg
Mass flow rate of steam = 5000 kg/hr = 5000 kJ/hr × 1 hr/3600 s = 1.389 kg/s
Maximum power generated = change in enthalpy × mass flow rate = 92 kJ/kg × 1.389 kg/s = 127.788 kJ/s = 127.788 kW
<u>Software Development and Client Needs</u>
In Incremental method of software development customers who do not have a basic idea of the development process are being carried along on like other methods that will relegate them to the background until a product is ready.
With this model and structure in place, when softwares/ products are built from several stages e.g prototype, testing, and when new features are added customers are always carried along with their valuable feedback and suggested greatly considered to achieve the customers satisfactions
This model will work well for the customers/clients who does not have a clear idea on the systems needed for their operations.
In summary the incremental model combines features from the waterfall and prototyping model.
For more information on soft ware development process kindly visit
brainly.com/question/20369682
Answer:
awnsers should be added to know to show additional
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.