Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .
Step-by-step explanation:
We assume that this is a normally distribution.
Given : The critical path length is 30 days .
i.e. Population mean = 
Variance : 
Then, standard deviation : 
Z-score : 
The value of z corresponding to 33 = 
Now, the p-value = 
Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.
Answer:
yes
Step-by-step explanation:
Answer:
Step-by-step explanation:
x+15+x+115+90=380 degree(sum of interior angles of four angles is 360 degree)
2x+220=360
2x=360-220
x=140/2
x=70 degree
52/41 in to decimal 1.2682
The answer is C. go with it.