Answer:
The correct option is D,$20,000 unfavorable
Explanation:
In the first place, it is noteworthy that fixed overhead flexible budget variance is the between the budgeted overhead cost and the actual fixed overhead incurred.
When actual fixed cost overhead is lower than budgeted,the resultant effect is a favorable variance,where the reverse is the case when the budgeted fixed overhead cost is higher as is the case here.
budgeted fixed overhead costs $200,000
Actual fixed overhead costs ($220,000)
fixed overhead flexible budget variance ($20,000) unfavorable
Answer:
Explanation:
The question says to complete the necessary adjusting entry
What is an adjusting entry:
An adjusting entry represent an accounting entry passed usually at the end of the accounting year to ensure that accounts following the matching principle. An adjusting entry can further be passed to calculate and bring in respective account balances at the end of the period.
Therefore, the required adjusting entry is as follows:
Date Particulars Debit Credit
Dec 30 Salaries expense $4,000
Salaries payable a/c $4,000
being the record of salaries accrued at the end of the year
Note: Since a day is $800 and there are 5 days, the accrual is $800 x 5 = $4,000
Answer:
$ - 1.96
Explanation:
After three months, Alice (long the contract) can buy the underlying by paying the delivery price of $40 which is $2 less than $42 the long position would have to pay if the contract was entered today.
DATA
Delivery price = $40
The three-month risk-free interest rate (with continuous compounding) =8%.
The current forward price = $42
Solution
So based on the present situation, Alice would be in $2 profit at the end of 3 months and Bob would be in $2 loss
Present value of Bob's loss (with continuous compounding) = 2\times e^{-0.08\times 0.25}
Present value of Bob's loss (with continuous compounding) = $1.96
The value of Bob's position is $ - 1.96
A project manager only focuses on the projects that the business wants to do and complete whereas an operational manager controls the operational side of the business. They should be kept apart because otherwise, their job requirements will get in the way of each other. I hope this helps!