The critical path is A-B-C, with a duration of 15 minutes.
<u>Explanation</u>:
- The critical path is A-B-C, with a term of 15 minutes. You don't need to be knowledgeable in computer lingo to make sense of this one (as I made sense of it absent a lot of data on that half of the condition). Here's the manner by which I made sense of this.
-
The main thing I saw was that "predecessor" was utilized, which implies something precedes the other thing. That provided me the primary insight that A precedes B and C, and that B must precede C. Then, I just included the term times for the three ways, which allowed me 15 minutes.
Answer:
Answer explained below
Explanation:
The value of here is 9
The value of there is hexadecimal value of DECO here, d = 0x39 aaaa (aaaa is the memory address of here )
We have the object code :-
let's take there address is 0x0007
0x0005 BR there :- 0x120020
0x0007 here: .WORD 9
310003 there: DECO here,d - 0x390007
310005 STOP
.END
Answer:
sorry not having idea about answer
Answer:
critical clearing angle = 70.3°
Explanation:
Generator operating at = 50 Hz
power delivered = 1 pu
power transferable when there is a fault = 0.5 pu
power transferable before there is a fault = 2.0 pu
power transferable after fault clearance = 1.5 pu
using equal area criterion to determine the critical clearing angle
Attached is the power angle curve diagram and the remaining part of the solution.
The power angle curve is given as
= Pmax sinβ
therefore : 2sinβo = Pm
2sinβo = 1
sinβo = 0.5 pu
βo =
⁰
also ; 1.5sinβ1 = 1
sinβ1 = 1/1.5
β1 =
= 41.81⁰
∴ βmax = 180 - 41.81 = 138.19⁰
attached is the remaining solution
The critical clearing angle =
≈ 70.3⁰