Answer:
d. 102.3 units ^2
Step-by-step explanation:
Evaluating the expression 11C3 is very simple to do.
If you are assuming that C is the notation for the combination.
11!
11C3= ____
3!(11-3)!
Answer:
The answer is option 2.
Step-by-step explanation:
You have to substitute the expressions into x :
h(x) = x + 4
h(x - 3) = (x - 3) + 4
h(x - 3) = x - 3 + 4
h(x - 3) = x + 1
Answer:
3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days
Well right off the bat, I can see a good reason why it should boggle.
If (x+y)=6 and (x-y)=2, then (x+y)(x-y) would be 12. It can't be 20.
The first 4 lines on the paper are inconsistent, so the question in the 5th line can't be calculated.
Another possible source of uncertainty (for us, anyway) is the remarkable similarity between the way you write ' Y ' and the way you write ' 4 ' . For example, look at the ' Y⁴ ' (I think ...) in the last line.