Answer:
0.726 is the probability that the project will be completed in 33 days or less.
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 30 days
Variance = 25 days
Standard Deviation,

We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.
Formula:

P(completed in 33 days or less)
Calculation the value from standard normal z table, we have,

0.726 is the probability that the project will be completed in 33 days or less.
Answer:
4.7/5
Step-by-step explanation:
100. This is very easy thanks teacher
9514 1404 393
Answer:
x = 6
Step-by-step explanation:
The sum of segments is used:
EF +FG = EG
3x +(5x +16) = 11x -2 . . . . substitute given expressions
8x +18 = 11x . . . . . . . . add 2
18 = 3x . . . . . . . . subtract 8x
6 = x . . . . . . divide by 3
The value of the variable is 6.
__
<em>Check</em>
The segment lengths are ...
EF = 3x = 3·6 = 18
FG = 5x+16 = 5·6 +16 = 46
EG = 11x -2 = 11·6 -2 = 64 = 18+46 . . . answer is correct