If General Contracting is sued by Rockville for refusing to complete the job, General Contracting can have the contract discharged on an impracticability basis.
<h3>What would make a contract impractical?</h3>
When parties to a contract agree to a contract that based on normal circumstances and due course, and one party discovers that they cannot complete the contract based on unforeseen circumstances, the contact can be ruled impractical.
General Contracting could not foresee the solid granite foundation and so they could not have known they would pay so much to complete the project. The contract can therefore be impracticable.
Find out more on impracticable contracts at brainly.com/question/10160005.
9 - f
10 - b
11 - d
12 - e
13 - c
14 - a
Answer: C. Carrie felt the strain of having to constantly fake positive emotions towards her customers
Explanation: Burn outs describes conditions where an individual becomes tired due to overwork. Carrie feeling the strain of having to constantly fake positive emotions towards her customers (due to her highly courteous nature) turned in her resignation as this can be very draining and can be seen as overwork.
Answer:
Hand saw is cheaper.
Explanation:
Given:
Material cost = $500
Electric saw cost rent per hour = $20
Building hour from electric saw = 6 hour
Building hour from hand saw = 15 hour
Time off pay from job = $8/hour
Computation of total cost from Electric saw :
Total cost from Electric saw = Material cost + Renting cost of electric saw + Time of from job
Total cost from Electric saw = $500 + (6 × $20) + (6 × $8)
Total cost from Electric saw = $500 + $120 + $48
Total cost from Electric saw = $668
Computation of total cost from hand saw :
Total cost from hand saw = Material cost + Time of from job
Total cost from hand saw = $500 + (15 × $8)
Total cost from hand saw = $500 + $120
Total cost from hand saw = $620
Hand saw is cheaper.
Answer:
motivate employees to support and contribute to innovation for competitive advantage