1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Leni [432]
3 years ago
5

6. Which devices of computer is known processing devices? las >​

Computers and Technology
2 answers:
bazaltina [42]3 years ago
8 0

Answer:

CPU is known as processing devices..!

Sholpan [36]3 years ago
6 0

Central processing unit (CPU) Graphics processing unit (GPU) Motherboard. Network card

You might be interested in
NO THIS ISNT ANY HOMEWORK!
IRISSAK [1]

Answer:

you can run minecraft on virtually anything with the lowest settings and optifine, as long as you dont use shaders or beefy texture packs

Explanation:

4 0
3 years ago
Read 2 more answers
01110111 01101000 01100001 01110100 00100000 01101001 01110011 00100000 00110001 00101011 00110001
Lera25 [3.4K]
Same lol thesis so me right now
7 0
4 years ago
30 POINTS !!!!!!!!
alex41 [277]

this should help! i read over the article a little bit and it seems to answer your question pretty well. https://www.snap.com.au/articles/the-pros-and-cons-of-digital-and-offset-printing.html

7 0
3 years ago
Does anyone else realize how the only tutor is for math never any other subjects?​
Slav-nsk [51]

Answer:

yes I do and I wonder why ??

7 0
3 years ago
For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish
laila [671]

Answer:

The correct option is A

Explanation:

In project management, earliest finish time for activity A refers to the earliest start time for succeeding activities such as B and C to start.

Assume that activities A and B comes before C, the earliest finish time for C can be arrived at by computing the earliest start-finish (critical path) of the activity with the largest EF.

That is, if two activities (A and B) come before activity C, one can estimate how long it's going to take to complete activity C if ones knows how long activity B will take (being the activity with the largest earliest finish time).

Cheers!

7 0
3 years ago
Other questions:
  • You have implemented nap with dhcp enforcement, so you need to ensure you have an updated anti-virus software package, an update
    7·1 answer
  • You are doing research for a current event report on smartphone technology. You do a web search for information that includes se
    5·2 answers
  • Three healthcare firms jointly own and share the same cloud resources to meet their computing needs. Which cloud model does this
    15·1 answer
  • When is e-mail an appropriate channel for goodwill messages? If you frequently communicate with the receiver by e-mail and are c
    15·1 answer
  • What is output by the following?<br><br>print (type("95"))
    13·1 answer
  • Write a program with a loop that lets the user enter a series of positive integers. The user should enter −1 to signal the end o
    7·1 answer
  • What is true regarding the cellular phone concept? a. a single radio broadcast tower system enables greater frequency reuse comp
    15·1 answer
  • Why would an information systems security practitioner want to see network traffic on both internal and external network traffic
    5·1 answer
  • For the following 4-bit operation, assuming these register are ONLY 4-bits in size, which status flags are on after performing t
    14·1 answer
  • Who watches Riverdale ? if you do can we be friends(pLEASE DON'T DELETE) and also who is your fav character from Riverdale
    8·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!