Cause and effect in the context of business cycle refers to actions done for a project in the business. Cause and effect may also refer to the stocks or market proceeds (e.g. Because of ____________, the proceeds were higher/lower).
Answer:
From a cost savings perspective the switch should be made in-house
Explanation:
In deciding whether Cool Systems should make or buy the switch , we calculate the relevant applicable to both situations,then compare t see which option saves costs.
The cost of making the switch is calculated thus:
Direct materials per unit $5
Direct labor $3
Variable overhead <u>$6</u>
Total relevant cost <u> $14</u>
The cost of purchasing the switch from another supplier is $15
From the above analysis, it is preferable to make the switch in-house as that option saves $1($15-$14) per switch.
However, it might be that we need to look beyond cost savings sometimes,purchasing the switch from another supplier might be viable if the quality of the outside switch is better or that the outside supplier can deliver in timely fashion.
Answer:
It is $329,209.31
Explanation:
Please attached sheet for computation.
Based on the PPC given, the points given would represent the following:
- Point B = Efficient use of resources.
- Point X = Impossible use of resources.
- Point A = Underutilized resources.
<h3>What do points on the PPC represent/</h3>
Points on the curve represent the efficient usage of resources because they show that all available resources are being used. Points B, C, and D are therefore all efficient.
Point X is impossible because all points outside of the PPC are not attainable due to a lack of resources. Point A shows that the available resources are not being fully utilized.
Options to describe the points:
- Efficient use of resources
- Under utilized resources
- Economic growth
- Trade-off
- Opportunity cost
Find out more on the PPC at brainly.com/question/2617319.
#SPJ1
Answer:$4,500---B, ie the 2nd option
Explanation:
From April to December we have 9 months
Interest Expense is given as Loan x Interest Rate x duration
Interest Expense = 50000 x 12% x 9/12 =
50,000x 0.12x9/12= $4,500