Answer:
The correct answer to the following question will be option C.
172.16.80.1-172.16.87.254
Explanation:
IP Address: IP Address stands for Internet Protocol Address, a unique numerical label allotted to every computer network that are connected to the network of the computer and communicate through the internet protocol.
- An IP address can be separated by periods and having four numbers that are called Octet. Range of IP address can be from 0 to 255.
- We have to keep the first 21 bits and start setting all from the 22nd bit on to 0 (zero).
- To get the suitable and the correct range of the address, we add and subtract 1 from the given broadcast address i.e.,172.16.85.0/21.
So, option C is the right answer and no other option is usable according to the given explanation and the address given by the administrator.
Answer:
6=110
13=1101
18=10010
27=11011
Explanation:
A decimal number is converted to binary number by constantly dividing the decimal number by 2 till the number becomes zero and then write the remainders in reverse order of obtaining them.Then we will get our binary number.
I will provide you 1 example:-
18/2 = 9 the remainder =0
9/2 = 4 the remainder =1
4/2 = 2 the remainder =0
2/2 = 1 the remainder =0
1/2 = 0 the remainder =1
Writing the remainder in reverse order 10010 hence it is the binary equivalent of 18.
<span>Arrival protocols are the type of data protocols that convert data into standard formats that can be used by applications, such as email, Web browsers and Skype</span>
Answer:
<h2>A negative impact.</h2>
Explanation:
The unemployed are also unable to purchase as many goods, so will contribute to lower spending and lower output. A rise in unemployment can cause a negative multiplier effect.
Answer:
The correct option is A
Explanation:
In project management, earliest finish time for activity A refers to the earliest start time for succeeding activities such as B and C to start.
Assume that activities A and B comes before C, the earliest finish time for C can be arrived at by computing the earliest start-finish (critical path) of the activity with the largest EF.
That is, if two activities (A and B) come before activity C, one can estimate how long it's going to take to complete activity C if ones knows how long activity B will take (being the activity with the largest earliest finish time).
Cheers!