1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
n200080 [17]
3 years ago
10

Mitch refuses to dine at a certain restaurant because he recalls reading two or three negative reviews of its service on a popul

ar website. Mitch is falling prey to:
Mathematics
1 answer:
Ghella [55]3 years ago
4 0

In this situation, we can actually see that Mitch was simply basing her taste on the information that is readily available to her. She does not even consider whether those reviews are legit or reliable. Mitch is falling into what we call as:

 

“the availability heuristic”

You might be interested in
Use the number line below to calculate 1/2x4/6:
Eddi Din [679]

Answer:

<h2>D.4/12</h2>

Step-by-step explanation:

<h3>I took the test to</h3>
4 0
3 years ago
A teacher offers 8 extra credit assignments. what is the domain of this graph?
UkoKoshka [18]

Answer:

C

Step-by-step explanation:

This is the shows the constant value on the X-axis

3 0
3 years ago
Help help help help help help
aleksklad [387]

I think it is 36 because you would have to multiply the numbers.

-Dhruva;)

4 0
3 years ago
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minute
Maurinko [17]

Answer:

Minimum cycle time = time for longest task = 2.4 minutes

Maximum cycle time = sum of the times to complete all the tasks = 18 minutes

Step-by-step explanation:

For the minimum cycle time, the reasoning is that all the tasks can be done simultaneously, at some during the assembling task. Hence, minimum time to complete one cycle is the time it takes to complete task that takes the longest time to complete.

For the maximum cycle time, the reasoning here is that each task is done after the completion of the previous task. The total time taken to finish the task will then be the sum of the time taken to complete each task. This usually is at the beginning of operations.

6 0
3 years ago
Does anyone know this ?
AnnyKZ [126]

Answer:

I think it is A, C, E I'm. it too sure, sorry if it's wrong

7 0
3 years ago
Other questions:
  • Two asteroids are 1000 km apart and are heading straight for each other. One asteroid is travelling at 59 km per second and the
    5·1 answer
  • If 5 4, − = x then x =<br> A. −21<br> B. −11<br> C. 1<br> D. 11
    9·1 answer
  • 3 1/2x + 215 = 495 Why is 3 1/2 multiplied by x in the equation
    15·1 answer
  • Avery has a total of $12.50 in her piggy bank at home. Each week she takes out $1.25 to ride the city bus. Write an equation rep
    10·1 answer
  • What is the slope of the line? x+3y=10
    11·1 answer
  • If x equals 12 what is the answer to the problem below?<br> X+43+2=?<br><br> Please help me !!
    11·2 answers
  • Select all the factors of:<br>x^2+ 3x - 10<br>A) (x-5)<br>B) (x+2)<br>C) (x-2)<br>D) (x+5)​
    8·1 answer
  • Simplify completely x2 + 4x - 45/x2 +10x+9 and find the restrictions on the variable.
    13·1 answer
  • Determine the LCM of 12 and 48.​
    13·1 answer
  • The graph shows the functions f(x), p(x), and g(x): 6.98 Ax) 1 p(x) 8(xx) US -9.06 10.94 -6.35 Courtesy of Texas Instruments Par
    5·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!