Answer:
Ceremony
Explanation:
Ceremony which can as well be reffered to as Rites and Rituals in an organization can be regarded as a pre-planned events which has social, formalities as well as latents purposes. This manifest purpose have effect on how the organization is working and in aiding the acheiving the organizational goals. It involves motivation of employee in the organization by giving bout award to the outstanding among them. For instance, On the foundation day of an organization, the president of the organization awards exceptionally performing employees with a bouquet and a plaque at a banquet every year is an example of a ceremony.
Answer: Micromarketing.
Explanation:
Micromarketing is applied by Land's end clothing company, where different tiny sections of a market are being targeted by the clothing designs and sizes produced. Micromarketing is form of marketing, where a smaller section of a large market is a company's target for sales.
Answer:
Treaty of Versailles
Explanation:
The terms which caused the most resentment in Germany were the loss of territory, the war guilt placed solely on Germany, the deliberate effacement of the German military and the demands of reparations.
Answered by NONE other than the ONE & ONLY #QUEEN herself aka #DRIPPQUEENMO!!!
HOPE THIS HELPED!!
Answer:
$100,000 and $241,000
Explanation:
The computation of the gross profit for the Black and Navy Divisions shown below:
As we know that
Gross profit = Sales - cost of goods sold
For Black, it would be
= $200,000 - $100,000
= $100,000
And, for Navy, it is
= $400,000 - $159,000
= $241,000
We simply applied the above formula to compute the gross profit
Answer:
We should select Project A as it has a higher expected value of 10,800 compared to Project B's expected value of 9,000.
Explanation:
We need to find the expected value of both the projects, using the formula
Expected value of project A= (probability of loss * value of loss)+(probability of gain* value of gain)
Expected value of project A= (0.40*-3,000)+(0.60*20,000)
=-1200+12,000=10,800
Expected value of project A= 10,800
Expected Value of project B= (probability of loss * value of loss)+(probability of gain* value of gain)
=(0.30*-5,000) +(0.70*15,000)=-1500+10,500=9,000