Answer:
$394 U
Explanation:
Calculation for the activity variance for vehicle operating cost in February would be
First step is to calculate the Flexible budget
Flexible budget= $1,880 + ($394 × 14)
Flexible budget=$7,396
Second step is to calculate the Planning budget
Planning budget= $1,880 + ($394 × 13)
Planning budget=$7,002
Last step is to calculate the activity variance for vehicle operating cost in Februar
Activity variance=Flexible budget $7,396-Planning budget $7,002
Activity variance=$394 U
Therefore The activity variance for vehicle operating cost in February would be closest to $394 U.
Hello!
.
The answer to your questions is "identifying stakeholders".
.
The main output of the identifying stakeholders process is the stakeholder register.
:)
Answer: Yes they will.
Explanation:
With high interest rates, the company will be able to make better returns if they invested the money and took advantage of those interest rates instead of spending the money on their project.
Assets like bonds will be better to go into because they will offer a return based on the higher interest rates which will bring in good returns.
The company is free to use those funds to invest in projects if these projects will lead to a better return than could be gotten from holding bonds but if that is not the case, they should simply buy bonds and hold them for superior returns.