Answer:
the first one
Step-by-step explanation:
A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
Answer:
Here you go, I think
Step-by-step explanation:
Volume of a cone = πr²h/3. π=3.14 R=radius. hope this helps you :)
The two is in the tenths place.
Answer:
4
Step-by-step explanation:
1st: do 2x3=6 so if 1 6in scoop makes one pitcher of tea then you could make about 4 pitchers of tea because there are the volume of the pitcher of tea mix is 24in so 24/6=4