1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
m_a_m_a [10]
3 years ago
11

Please answer this right

Mathematics
1 answer:
bearhunter [10]3 years ago
3 0
0.06 of a second or six-hundredths
You might be interested in
ASAP please help due in the morning
Alex Ar [27]
Okay be a helpin’ hand
7 0
2 years ago
Read 2 more answers
:///////////////////////////////////////////////////////////// Math
allochka39001 [22]

Answer:

12 inches per foot.

Step-by-step explanation:

It's just like how the question was stated from above! No need to over think this question.  .ω.

Hope this helps!

8 0
3 years ago
Read 2 more answers
An online video store charges $24 please help
mr Goodwill [35]

Answer:

B. 24d + 4; $76

Step-by-step explanation:

Part 1: If the online store charges $24 per DVD, this is the same as saying "24 multiplied by the number of DVDs bought".

It's given that "d" represents the number of DVDs

  • So the first part of the variable expression is: 24d

If the online store also charges an additional $4 per <em>order,</em> that means that it's only $4 extra for the whole order. NOT per DVD you buy.

  • Result: 24d + 4

Part 2: If someone were to buy 3 DVDs, that would mean that d = 3.

To find the total cost, substitute 3 for d into the expression.

  • 24d + 4
  • 24(3) + 4
  • 72 + 4 = 76
  • Result: $76
4 0
3 years ago
A construction manager needs 12 workers to complete a building project in 54 days. Find in terms of T the number of workers need
ch4aika [34]

Answer:

<h3>2T/9</h3>

Step-by-step explanation:

A construction manager needs 12 workers to complete a building project in 54 days, we can write;

12 workers = 54 days

T find the number of workers needed to complete the same project in T days, we will write;

x workers = T days

Divide both equations

12/x = 54/T

Cross multiply

12T = 54x

x = 12T/54

x = 2T/9

Hence the number of workers needed to complete the same project in T days is 2T/9 workers

7 0
3 years ago
Which ratio is equivalent to 1 to 8?<br> 7 to 14<br> 7 to 9<br> 6 to 41<br> 6 to 48
Ivan

6 to 48 simplified

it becomes 1 to 8

so the answer is 6 to 48

plz mark as brainliest

5 0
2 years ago
Read 2 more answers
Other questions:
  • Simplify:<br> 6xy/X^2-y^2 - x+y/x-y
    13·1 answer
  • What is the slope of the line?
    5·1 answer
  • PLEASE HELP ME I NEED THIS QUICKLY
    9·2 answers
  • inez collects data from 30 students about the number of pets they have.she find the mean number of pets and determines that the
    6·1 answer
  • I need to find the slope and b <br> Y=mx+b <br> HELP ME
    11·1 answer
  • The auditorium where the spring musical will be performed has 10 seats in the 1st (front) row. Each row behind the Ist row has 4
    11·2 answers
  • Simplest form of ratio 24:36:60​
    11·1 answer
  • Hurry please help!!!!
    8·1 answer
  • Savings account at a bank pays 5% simple interest in account at Bank B pays 2% compounded interest the table shows the balance i
    14·1 answer
  • Can someone please help me with this page, it woule help me out so much !!
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!