This is what i found Answer 1
Risk-Adjusted Asset Base
The calculation of the risk-adjusted asset base for a bank is as below-
Risk-adjusted asset = (Cash × 0%) + (municipal security × 20%) + (home mortgages × 50%) + (Commercial loans × 100%)
= (20 × 0%) + (100 × 20%) + (500 × 50%) + (300$ × 100%)
= 0 + 20 + 250 + 300
= $570 million
The outcome shows that the risk-adjusted or weighted asset based for the bank will be $570 million.
Tier1 and Tier 2 Capital:
If the bank has no off-balance sheet activity then minimum required level of Tier 1 and Tier 2 capital will be-
Tier 1 capital = Risk-weighted asset × 4%
= $570 × 4%
= $22.8 million
Tier 2 capital = Maximum of 1.25% of risk-weighted asset
= $570 × 1.25%
= $7.125 million
Total capital = $22.8 + $7.125 => $29.925 million
The outcomes indicate that the minimum required level of Tier1 and Tier
2 capital is $22.8 million and $7.125 million for the bank.
Bank Comply with Capital Requirements:
If the bank has Tier 1 capital of $25 million and Tier 2 capital of $15
million then it will comply with its capital requirements of $29.925
million. It is because in this situation, total capital of bank is $37
million that is higher than the above calculated capital of $29.925
million.
Impact of off-Balance Sheet Activities on Capital Requirements
The addition of off-balance sheet activities might increase the capital
requirement of the bank. It is because an off-balance sheet items is a
financial contract that can create credit loss for the company due to
credit risk. So, in case of adding off-balance sheet activities, a bank
will require more capital to cover credit loss. Along with this, it can
also increase the minimum ratio of capital to risk-weighted assets from
8% and in that situation; the bank will need more capital (Carmichael
& Graham, 2012).
Answer 2
Probability of Repayment and Risk Premium
A).
If the rate on a one-year treasury bill is 6% and in case of loan
default, no payments are expected on financial securities then the
probability of repayment and the risk premium on 1 year AA-rated loan
yielding 9 percent will be-
Probability of Repayment:
The following formula can be useful to determine probability of repayment.
P = (1 + I) / (1 + k)
Where,
I = 6%
k = 9%
Then, ...you have $2.19 left :D
Answer:
Total sales variance $87,340 Favorable
See report below
Explanation:
The sales budget for the month of June would like as follows:
Budgeted Sales
Product units Price Total($)
A 40,000 $7 280,000
B 39,000 $9 351,000
Actual sales
Product units Price Total($)
A 39,000 $7.10 276,900
B 49,600 $8.90 441440
Sales Budget Report for the month of June 2019
Budget Actual Variance ($)
A 280,000 276,900 3,100 Unfavorable
B 351,000 441,440 <u>90,440 </u>favorable
Total sales variance <u> 87,340 Favorable</u>
Answer:
A) giving the key to a safe-deposit box where the gift is kept
Explanation:
- A Constructive delivery possession is that acquisition when here a symbolic transfer of property. The constructive distribution of the possession is basically a right that the property is not actually managed
- But the donor has done something to convey the possession, but the property is of such a nature that physical possession is then not possible, the creative possession of the property is sufficient to carry out the act of gift.
Answer:
a-The present value of revenue in the first year is $61,085.92.
b-The total time it would take to pay for its price is 2.44 years of 29.33 months.
Explanation:
a-
Let the function of the revenue earned is given as
Here
- a and b are the limits of integral which are 0 and 1 respectively
- r is the rate of interest which is 5% or 0.05
- S(t) is the function of value which is
So the present value of revenue in the first year is $61,085.92.
b-
The time in which the machine pays for itself is given as
The present value is set equal to the value of machine which is given as
$160,000 so the equation becomes:
So the total time it would take to pay for its price is 2.44 years of 29.33 months.
Answer:
The NPV = $1578.185602 rounded off to $1578.19
As the NPV is positive, the project should be accepted.
Explanation:
The Net Present Value or NPV is a tool used to evaluate projects. It is used with various other tools to decide whether to undertake a project or not. To calculate the Net Present Value or NPV, we take the present value of the cash inflows provided by the project and deduct the initial cost of the project. If the NPV is positive, we should proceed with the project and vice versa.
NPV = CF1 / (1+r) + CF2 / (1+r)^2 + ... + CFn / (1+r)^n - Initial Cost
Where,
- CF1, CF2, ... represents cash flow in Year 1, Year 2 and so on.
- r is the required rate of return
NPV = 3200 / (1+0.17) + 3200 (1+0.17)^2 + 3200 (1+0.17)^3 +
3200 (1+0.17)^4 + 5700 (1+0.17)^5 - 9800
NPV = $1578.185602 rounded off to $1578.19