Answer:
3.066543
Step-by-step explanation:
This number is between 3.077243 and 3.0721
It took them 4 days to install 480 chairs which means if they were working at a constant rate they got 120 chairs installed daily. with 360 chairs left that means in 3 days they will finish. so overall, it took the workers 7 days to finish, or a week.
Answer:
C)
Step-by-step explanation:
f(n) = 26 + 9(n-1)
There are a couple of things you didn't mention.
In order to come up with an answer to the question,
I have to assume reasonable numbers for them, and
then answer the question that I have invented.
Assumption #1: Each day that you work, you work for 8 hours.
Assumption #2: You work for three days each week.
If those assumptions are true, then you earn
($7.25 / hour) x (8 hours/day) x (3 days/week) x (2 weeks) =
($7.25 x 8 x 3 x 2) = $348 before taxes and other deductions.