an electrician was hired to wire a new house. In 11 1/4 days he estimates he has completed 70% of the job. At his current pace o
f work, how long will it take him to complete the entire job?
1 answer:
It will take him about 16.07 days.
To solve this problem, you can write a proportion to find the amount of time.
11.25 days / 70% = x days / 100%
If you cross multiply and divide this, you will get about 16.07.