Answer:
$6,765
Explanation:
The total cost for job K913 is given by the sum of the costs with manufacturing overhead (fixed and variable), direct materials (M) and direct labor (L).
Since the company uses a predetermined overhead rate based on direct labor-hours, the overhead cost for job K913 is:

The total cost for the job is:

The total job cost for Job K913 is closest to $6,765.
Answer: The answer is given below
Explanation:
a. . Private saving
Private saving=Y+TR-C-T
= $11t + $1t - $8t - $3t
= $12 trillion - $11 trillion
= $1 trillion
b. Public saving
Public Saving= T-G-TR
Since G is not given, we can use:
I = public saving + private saving
$2t = public savings + $1t
Public saving= $2 trillion - $1 trillion
Public savings = $1 trillion
c. Goverment purchases
Since public savings = T - G - TR
$1t = $3t - G - $1t
G = $3t - $1t - $1t
G = $3 trillion - $2 trillion
G = $1 trillion
d. The goverment budget deficit or budget surplus.
There is a budget surplus of $1 trillion which has been calculated in the public savings.