Answer:
(a) 2min/15units
(b) 1min/20units
(c) The bottleneck stage is cutting. The process capacity is 450units/hour
(d) The capacity of the new employee should be 1unit/2sec. The process capacity will increase four times
Step-by-step explanation:
(a) Cycle time for stage cutting for 2 employees = 16sec/2units × 1min/60sec = 2min/15units
(b) Cycle time for stage sealing for 1 employee = 3sec/1unit × 1min/60sec = 1min/20units
(c) Process capacity of stage cutting = 15units/2min × 60min/1hour = 450units/hour
(d) If the capacity of the new employee is 1unit/2sec, the process capacity = 1unit/2sec × 3600sec/1hour = 1800units/hour. The process capacity increases 4 times (1800/450 = 4)
Answer:8.5
Step-by-step explanation:
Pythagorean Theorem
A
a^2 + b^2 = c^2
3^2 + 8^2 = c^2
9 + 64 = c^2
73 = c^2
C= Sqrt (73)
C = 8.5
Craig earns $2.50 per hour plus $3.50 for each hair cut he gives.
He worked for 7 hours.
In hour basis, he earned

He gave 4 hair cuts.
For 4 haircuts, he earned

So, he total earned

Hence, the correct option is (A).
Each ticket would be worth $12.60