Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
244
Step-by-step explanation:
Answer:
Step-by-step explanation:
<u>It is assumed the angles A and C are congruent:</u>
- 3x + 40 = x + 50
- 3x - x = 50 - 40
- 2x = 10
- x = 5
m∠A = 3*5 + 40 = 55°
Answer:
-19x
Step-by-step explanation:
Answer:

Step-by-step explanation:
1) if the required straight line is 'l', the given point is A(a;b), then the required equation of line can be written in form:

where (x₁;y₁) is other point B, which belongs to the 'l';
2) from the equation it is possible to detect the coordinates of the perpendicular, they are (x₁-a;y₁-b);
3) if the given perpendicular is ax+by=5, then the coordinates of the vector (a;b) are coordinates of the vector, which belongs to the required line 'l', and then: x₁-a=a and y₁-b=b;
4) if to substitute the a=x₁-a and b=y₁-b into the required equation of line 'l', then:

5) finally, the equation is: ay=bx, or y=b/a *x (slope-interception form).
note: the suggested solution is not the only way.