Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Ok, so for this you're likely graphing in y=mx+b format (slope intercept). So to start, you'all first subtract 3x from the equation to get 6y=-3x+16. Now you'll divide the equation by 6 to get y alone. Your final equation will be y=-1/2x+16/6
0.19 for one cookie and 0.59 for one doughnut
x for how much one cookie costs and y for how much one doughnut costs
6x+4y=3.5
12x+5y=5.23
solve by substitution: (elimination would work too)
4y=3.5-6x
y=0.875-1.5x
12x+5(0.875-1.5x)=5.23
12x+4.375x-7.5x=5.23
4.5x=0.855
x=0.19
now use x to solve for y:
6(0.19)+4y=3.5
1.14+4y=3.5
2.36=4y
y=0.59
Check the work: 6(0.19)+4(0.59)=3.5