Answer:
how many people were asked though
Explanation:
Answer:
a) Ql=33120000 kJ
b) COP = 5.6
c) COPreversible= 29.3
Explanation:
a) of the attached figure we have:
HP is heat pump, W is the work supplied, Th is the higher temperature, Tl is the low temperature, Ql is heat supplied and Qh is the heat rejected. The worj is:
W=Qh-Ql
Ql=Qh-W
where W=2000 kWh
Qh=120000 kJ/h
b) The coefficient of performance is:
c) The coefficient of performance of a reversible heat pump is:
Th=20+273=293 K
Tl=10+273=283K
Replacing:
The first one is d or the 4th answer choice and the second one is false. Hope this helps!
Answer:
The code is attached.
Explanation:
I created a string s including 6 colors with spaces in between. Then I converted the string into a list x by using split() method. I used three different methods for removing elements from the list. These methods are remove(), pop() and del.
Then I used methods append(), insert() and extend() for adding elements to the list.
Finally I converted list into a string using join() and adding space in between the elements of the list.
Answer:
c) site preparation
Explanation:
A construction process can be defined as a series of important physical events (processes) that must be accomplished during the execution of a construction project.
Generally, in the construction of any physical asset such as offices, hospitals, schools, stadiums etc, the first step of the construction process is site preparation. Site preparation refers to processes such as clearing, blasting, levelling, landfilling, surveying, cutting, excavating and demolition of all unwanted objects on a piece of land, so as to make it ready for use.
This ultimately implies that, site preparation should be the first task to be accomplished in the construction process.
Hence, the construction process typically begins with site preparation before other activities such as the laying of foundation can be done.
Additionally, construction costs can be defined as the overall costs associated with the development of a built asset, project or property. The construction costs is classified into two (2) main categories and these are; capital and operational costs.