Answer: Extra safety that is applied to a project immediately before the use of the constrained resource.(D)
Explanation:
Drum buffer can be explained as period of time that is used to safeguard the drum resource from the problems that occur from the drum operation.
The aim of the drum buffer effect is to provide a recheck of the work in order not to deviate from the real aim of the project. The buffer makes up for the process variation, and makes the project stable as it gives extra safety which is applied mmediately before using constrained resource.
Answer:
C. Scenario Analysis
Explanation:
Scenario Analysis is analysis of computing the Net Present Value by changing various variables, that is change in values of Sales, Variable Cost, Revenue, Cost of project and various other things. Basically it measures the Net Present Value with respect to various factors associated with calculating the net present value, as Jamie is calculating Net Present Value with different factors, that is in different scenarios, it is called Scenario Analysis.
Debit Accounts Receivable $5,000; credit Tile Sales $5,000
Answer:
Explanation:
Ethics demands reasons to be given for changing from one depreciation method to another. There are three depreciation methods that are applicable including double-declining balance technique, unit of production technique, and straight-line technique.
Changing from one depreciation method to another must be done in the best interests of shareholders and reasons for such a change must be disclosed. Therefore, ethics requires a company to reveal the changes in depreciation method and adhere to the accounting principles related to the method used.