1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
mojhsa [17]
3 years ago
5

Which equation could have the graph shown below?

Mathematics
1 answer:
mars1129 [50]3 years ago
6 0

Answer:

  1. y = ( x +4)(x +1 )(3_x

Step-by-step explanation:

because the line were there

You might be interested in
What is the slope of y-3=-2(x+5)
BigorU [14]

Answer: slope (m) = -2

Step-by-step explanation:

y-3=-2(x+5)

put it into y=mx+b

use PEMDAS-Parantheses, Exponents, Mult. Div. Add. Sub. for your order of operations.

first, parantheses.

-2(x+5)

-2 times x = -2x

-2 times 5 = -10

your new equation is y-3 = -2x-10

now, to get y by itself, cancel out the -3 by adding a positive 3 to both sides.

you final equation will be y=-2x-7

in the form y=mx+b, m is your slope.

therefore, -2 is your answer, or slope.

8 0
2 years ago
Ed wants to bicycle at least 75 miles this week. The inequality 11 + 4b > 75 can be used to find the average number of miles
jeyben [28]

Answer: Ed should bike at least more than 16 miles

Step-by-step explanation:

11 + 4b > 75

4b > 64

b > 16

5 0
3 years ago
Read 2 more answers
HELp <br> Which relation is a function?
madreJ [45]
It is the first one because you can use the vertical line test to see that it doesn’t hit more than one point per x-value
7 0
3 years ago
Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem
jasenka [17]

Answer:

The risk consequence of both activities is 1.6 months.

Step-by-step explanation:

We can define a randome variable D: total delay time for the project, and calculate its expected value.

This would be the risk consequence of both activities.

The expected delay time for the project is the sum of the expected delay for task A plus the expected delay for task B. It is assumed the likelihood of a problem in any task is independent of the other.

Then, each expected delay for a task is equal to the probability of a problem multiplied by the consequence (delay time).

E(D)=E(D_a)+E(D_b)=p_aT_a+p_bT_b\\\\E(D)=0.5*2+0.2*3=1+0.6=1.6

The risk consequence of both activities is 1.6 months.

6 0
3 years ago
WILL GIVE BRANLIEST PLEASE ANSWER
LiRa [457]

Answer:

The correct answer is b.

Step-by-step explanation:

1/8= 0.08

18%=0.18

4 0
4 years ago
Read 2 more answers
Other questions:
  • If two points on line l above have coordinates (0, A) and (2, −3), and the slope of the line is A, then what is the value of A?
    7·1 answer
  • Can someone help me with math?
    7·2 answers
  • A bage contains 5 blue marbles, 3 red marbles, and 2 yellow marbles. You select a marble at radom. What is p(yellow)
    14·1 answer
  • Can someone help me??? i get almost all of the unit but not this one part
    11·1 answer
  • C) 4c°+4c°+16c°+90°=360°
    6·2 answers
  • A baker decorates 42 cupcakes in 30 minutes. She decorates cupcakes at a constant rate how many can the baker bake per minute
    13·1 answer
  • Put the quadratic
    12·1 answer
  • The coordinate point F(-8, 0) after a dilation with scale factor of 0.25, centered at the origin, becomes the point
    7·1 answer
  • Sally went scuba diving, she started at sea level, then dove 14 meters before rising 3 meters. What is her current depth?​
    7·1 answer
  • suppose we fit the least-squares regression line to a set of data. the plot of the residuals is given below. plot of residuals t
    9·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!