1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
puteri [66]
3 years ago
12

Blue Enterprises reported cost of goods sold for 2020 of $1,307,500 and retained earnings of $5,383,000 at December 31, 2020. Bl

ue later discovered that its ending inventories at December 31, 2019 and 2020, were overstated by $118,630 and $36,930, respectively. Determine the corrected amounts for 2020 cost of goods sold and December 31, 2020, retained earnings.
Business
1 answer:
Sphinxa [80]3 years ago
4 0

Answer: See explanation

Explanation:

Based on the information given in the question, the corrected amounts for 2020 cost of goods sold would be:

= $1307500 + $36930 - $118630

= $1225800

The corrected Retained earnings would be:

= $5,383,000 - $36,930

= $5,346,070

You might be interested in
Custom Engines Company has the following estimated costs for the upcoming​ year:
Lelechka [254]

Answer:

$22

Explanation:

The computation of the predetermined manufacturing overhead rate per hour is shown below:

= Total Factory overhead ÷ Estimated labor hours

where,

Total factory overhead is

= Salary of factory supervisor + Heating and lighting costs for factory + Depreciation on factory equipment

= $37,000 + $22,300 + $5,600

= $64,900

And, the machine hours is 2.900

So, the predetermined overhead rate is

= $64,900 ÷ 2,900

= $22

This is the answer but the same is not given in the options

6 0
2 years ago
A customer has requested that Lewelling Corporation fill a special order for 2,400 units of product S47 for $36 a unit. While th
yKpoI14uk [10]

Answer:

Effect on income= $38,640 increase

Explanation:

Giving the following information:

Units= 2,400

Seling price= $36

Variable cost per unit:

Direct materials $4.80

Direct labor 4.00

Variable manufacturing overhead 1.90

Total variable cost= 10.7

Increase in variable cost= $1.70

Increase in fixed costs= $18,000

<u>Because it is a special offer, there is unused capacity, and other sales will not be affected, we will take into account only the incremental fixed costs (besides the variable costs).</u>

Sales= (2,400*36)= 86,400

Total variable cost= 2,400*(10.7 + 1.7)= (29,760)

Increase fixed costs= (18,000)

Effect on income= $38,640 increase

6 0
3 years ago
The problem now is to decide which contractor to choose.B has indicated that for another $20 million he could do the job in 18 m
Ede4ka [16]

Question: The question is incomplete. See the full question below and the answer.

You are an up-and-coming developer in downtown Seattle and are interested in constructing a building on a site you own. You have collected four bids from prospective contractors. The bids include both a cost ($millions) and time to completion (months):

Contractor    Cost           Time

A                   100             20

B                    80              25

C                    79               28

D                   82                26

The problem now is to decide which contractor to choose. B has indicated that for another $20 million, he could do the job in 18 months, and you have said that you would be indifferent between that bid and the original proposal. In talking with C, you have indicated that you would just as soon pay her an extra $million if she could get the job done in 26 months. Who gets the job? Explain your reasoning. (It may be convenient to plot the four alternatives on a graph.)

Answer:

See the explanation for the answer and find attached of the graph.

Explanation:

So we draw a regression line of Time vs Cost and best fit a curve based on the data given, given in the above figure. The four alternatives are marked in the figure as well. Our main objective is to reduce both time and cost, but that might not be possible So the best thing would be to look for alternatives which lie below the line. If C gets an extra million, then that point would come below the regression line, and it would be a better alternative than D, because for the same time we are getting the job done at a cheaper cost.

Also if B is paid extra 20 million, that point also comes below the regression line, and hence will be a better alternative than A because for the same cost again we are getting the job done earlier. We need to choose between B and C. Now in order to optimise both cost and time, we need to choose a point close to the middle point of the regression line segment in 1st quadrant. We see that C is much more closer to the middle point and hence seems like a better option.

So we choose C as our contractor if we consider B's alternative bid, but if we do not consider B's alternative bid and stick to the original one, we choose B as our contractor.

8 0
3 years ago
A delivery company is considering adding another vehicle to its delivery fleet; each vehicle is rented for $100 per day. Assume
ollegr [7]

Answer:

a. What is the MRP? What is the MRC? Should the firm add this delivery vehicle?

marginal revenue product = marginal product of labor x marginal revenue per output unit

MRP = 1,500 packages x $0.10 per package = $150

marginal resource cost (MRC) = $100 (the cost of renting the delivery truck)

The company should add the delivery truck because MRP is higher than MRC.

b. Now suppose that the cost of renting a vehicle doubles to $200 per day. What are the MRP and MRC in this situation?

MRP = $150 (doesn't change from question a)

MRC = $200 (the cost of renting the delivery truck)

The company should not add the delivery truck because MRP is less than MRC.

c. Next suppose that the cost of renting a vehicle falls back down to $100 per day, but, due to extremely congested freeways, an additional vehicle would only be able to deliver 750 packages per day. What are the MRP and MRC in this situation? Would adding a vehicle under these circumstances increase the firm's profits?

MRP = 750 packages x $0.10 per package = $75

MRC = $100

The company should not add the delivery truck because MRP is less than MRC.

8 0
3 years ago
Bailey Company's flexible budget cost formula for indirect materials, a variable cost, is $0.60 per unit of output. If the compa
kolezko [41]

Answer:

$4,600

Explanation:

Standard rate = $0.60

Unit produced = 9,000

Favorable spending variance = $800

Material spending variance = [Standard rate - Actual rate) * Unit produced

Material spending variance = [Standard rate*Unit produced - Actual rate*Unit produced

$800 = [$0.6*9000) - Actual cost

Actual cost = [$0.6*9000) - $800

Actual cost = $5,400 - $800

Actual cost = $4,600

4 0
2 years ago
Other questions:
  • ________ and their members provide value because they buy and sell securities on behalf of the companies and individuals they re
    12·1 answer
  • Because other firms are willing to pay to advertise with them, suppliers of nonrival private goods often modify their products t
    12·1 answer
  • (Life-Cycle Hypothesis) According to the life-cycle hypothesis, what is the typical pattern of saving and spending for an indivi
    7·1 answer
  • The manager of the Beach Division of Treat Time is evaluating the acquisition of a new mobile ice cream server. The budgeted ope
    9·1 answer
  • Kim's Egg Rolls were being promoted as a dinner item but after a few years the company decided to change their packaging and adv
    12·1 answer
  • E3-17 (Algo) Calculating Equivalent Units, Unit Costs, and Cost Assigned (Weighted-Average Method) [LO 3-3] Vista Vacuum Company
    7·1 answer
  • 17. What positive outcomes are associated with<br> saving money and why?
    5·2 answers
  • On June 1, Crane Company Ltd. borrows $99,000 from Acme Bank on a 6-month, $99,000, 8% note. The note matures on December 1. Cor
    13·1 answer
  • (1) Quality of products available in superstore.
    6·1 answer
  • A
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!