The correct answer is 10 days.
Step-by-step explanation:
To fill a trench, 5 men work for 6 hours a day for eight days.
Total work hours required is given by 5 × 6 × 8 = 240 hours.
The same work is supposed to be done by 3 men working 8 hours a day.
Let these three men need to work for x days.
Therefore total work hour these group of three men gave = 3 × 8 × x = 24x hours
Therefore the work hour of both the group of 5 men and 3 men should be equal.
⇒ 24x = 240
⇒ x = 10
Therefore the group of 3 men have to work for 10 days to fill the trench.
<span>3x=7y+16
15y=7y + 16
15y - 7y = 16
8y = 16
y = 8/16
y = 2
hope this helps you !!! =')</span>
Wouldn't it be
3:2
since there's 3 for 2
and then for 12 you would get
12:8
I'm not 100% sure, as we don't do this at school here, but I think its :
1) 3 units right, 2 units down
2) (x, y) > (x-12, y+3)
3) (x, y) > (x+9, y-8)