Answer:
y 0.4
x 0.3
Step-by-step explanation:
Answer:
37.699 cubic inches of water
Step-by-step explanation:
Volume of a cone is V= 1/3 pi r^2 h
We are given that the height is 5 in and the radius is 2 in.
Plug that into the formula: V= 1/3 pi 2^2 9
1/3 x 4 x 9 = 12
Now we are left with 12 pi.
Use a calculator and multiply 12 by pi to get:
37.699
Answer:
3
Step-by-step explanation:
The equation of a parabola in vertex form is
y = a(x - h)² + k
where (h, k) are the coordinates of the vertex and a is a multiplier
Here (h, k) = (2, - 4) , thus
y = a(x - 2)² - 4
To find a substitute (3, - 1 ) into the equation
- 1 = a(3 - 2)² - 4 ( add 4 to both sides )
3 = a
Thus
y = 3(x - 2)2 - 4 ← equation in vertex form
= 3(x² - 4x + 4) + 4
= 3x² - 12x + 12 + 4
= 3x² - 12x + 16 ← equation in standard form
with coefficient of x² term = 3
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.