Answer:
Mortgage/rent.
Homeowners or renters insurance.
Property tax (if not already included in the mortgage payment).
Auto insurance.
Health insurance.
Out-of-pocket medical costs.
Life insurance.
Electricity and natural gas.
Explanation:
Answer:
A roller coaster does not have an engine to generate energy. This builds up a supply of potential energy that will be used to go down the hill as the train is pulled by gravity. Then all of that stored energy is released as kinetic energy which is what will get the train to go up the next hill.
Explanation:
Answer:
The curve length (<em>L</em>) will be = 1218 ft
The elevations and stations for PVC and PVI
a. station of PVC = 103 + 91.00
b. station of PVI = 116 + 09.00
c. elevation of PVC = 432.18ft
d. elevation of PVI = 426.09ft
Explanation:
First calculate for the length (<em>L</em>)
To calculate the length, use the formula of "elevation at any point".
where, elevation at any point = 424.5.
and ∴ PVC Elevation = (420 + 0.01L)
Then, calculate for Station of PVC and PVI and elevation of PVC and PVI
Answer:
c) site preparation
Explanation:
A construction process can be defined as a series of important physical events (processes) that must be accomplished during the execution of a construction project.
Generally, in the construction of any physical asset such as offices, hospitals, schools, stadiums etc, the first step of the construction process is site preparation. Site preparation refers to processes such as clearing, blasting, levelling, landfilling, surveying, cutting, excavating and demolition of all unwanted objects on a piece of land, so as to make it ready for use.
This ultimately implies that, site preparation should be the first task to be accomplished in the construction process.
Hence, the construction process typically begins with site preparation before other activities such as the laying of foundation can be done.
Additionally, construction costs can be defined as the overall costs associated with the development of a built asset, project or property. The construction costs is classified into two (2) main categories and these are; capital and operational costs.