Answer:
D.) $75,000
Explanation:
Amount of revenue recognized = Cost incurred to date / Estimated total cost * Contract price
Cost incurred to date=60,000
Estimated total cost=400,000
Contract price=500,000
Amount of revenue recognized= 60,000/400,000 * 500,000
=0-15 * 500,000
=$75,000
Amount of revenue recognized in year 1 is $75,000
Answer:
a) demand curve and demand schedule
Explanation:
A demand schedule is actually a table while a demand curve is a graph. Understanding the difference between the two of them is important in answering this question but both show different quantities of goods that consumers are willing to buy at different prices. An important assumption is that other factors affecting the quantity demanded are held constant. In summary, a demand schedule shows this relationship in a tabular form while demand curve shows it in a graphical form.
Answer:
D. outbound logistics
Explanation:
The rest are secondary activity in Porter's value chain model.
Answer:
physical strength
professional appearance
hospiltality certifacation
attention to detail