The speed is equal to the area under the line up to the point where t .=15 s.
Do find the area of the triangle and that if the rectangle and add them together.
The area of the triangle is 25 and the rectangle is also 25 so the speed is 50 m/s
Answer:
Use the principle of momentum
Initial momentum = final momentum
Momentum formula = Mass * Velocity
Explanation:
Answer:
Wavelength, 
Explanation:
Given that,
Number of cycles in a spiral spring is 2.91 in every 3.67 s
The velocity of the pulse in the spring is 0.925 cm/s, v = 0.00925 m/s
To find,
Wavelength
Solution,
Number of cycles per unit time is called frequency of a wave. The frequency of the longitudinal pulse is,

The wavelength of a wave is given by :



So, the wavelength of the longitudinal pulse is 0.011 meters. Hence, this is the required solution.
Question:
The operations manager for a well-drilling company must recommend whether to build a new facility, expand his existing one, or do nothing. He estimates that long-run profits (in $000) will vary with the amount of precipitation (rainfall) as follows:
Alternative Precipitation
Low Normal High
Do nothing -100 100 300
Expand 350 500 200
Build new 750 300 0
If he feels the chances of low, normal, and high precipitation are 30 percent, 20 percent, and 50 percent respectively, What is EVPI (Expected value of Perfect Information)?
A. $140,000
B. $170,000
C. $285,000
D. $305,000
E. $475,000
Answer:
D. $170,000
Explanation:
The expected long run profits are for
Low Normal High
Do nothing -100*0.3 100*0.2 300*0.5 = 140
Expand 350*0.3 500*0.2 200*0.5 = 305
Build new 750*0.3 300*0.2 0*0.5 = 285
Therefore the expected long run profits are
$140,000
$305,000
$285,000
Based on his selected option being either to build new or to expand, the most profitable option is to expand
=$305,000
EVPI = EPPI-EMV =$170,000