Answer: I cant tell if that is a 626,634 or two numbers 626 and 634 so ill give both answers.
626,634 rounded to the nearest ten is 626,630.
626 rounded to the nearest ten is 630.
634 rounded to the nearest ten is 630.
Plz mark brainliest:)
Answer:
3y
Step-by-step explanation:
Answer:
Jim's path is the critical path on this activity graph.
Step-by-step explanation:
Critical Path:
Critical path is the the longest path in the project task paths. It shows the least amount of time in which project can be completed. It can be find by looking at the longest path in the network diagram of the project; not in term of nodes or activities instead in term of days.
In given case:
Path 1 Bill task's total duration= 6 days
Path 2 Jim's task's total duration= 17 days
Path 3 Betty task's total duration= 7 days
Path 4 Cynthia task's total duration= 14 days
Hence the longest path i.e. critical path is of Jim's activity path !
The answer is J) $7.75 since you divide the price by 8.
Answer:A: last option
B: second option
C: third option
D: first option
Step-by-step explanation: