(a) The production schedule is 4000 hour per year, or 240,000 minutes. In that time, 133,333 1/3 parts can be produced. The production of 500,000 parts in a year will require the use of ...
.5 million/(.1333... million/machine) = 3.75 machines
The demand can be satisfied by 4 machines.
__
(b) If availability is 95% then 3.75/0.95 ≈ 3.95 machines will be required.
The demand can be satisfied by 4 machines.
Answer:
Planned maintenance refers to any scheduled activity carried out to check a machine is working ok and diagnose procedures to fix it if need it. On the other hand, predictive mainteance is all the techniques which help to define if a machine requires or not maintenance activities so far.
Explanation:
Planned maintenance is based on preventive routines to ensure a machine is working in acceptable conditions and at the same time prevent them to change to risky values performing acticities like parts replacement, cleaning, etc. The key of this maintenance is schedule, that is to say, is a maintenance that has to be carried out constantly each certain time. Predictive maintenance is different because it is used to define if a machie needs any kind of inspection or if, on the contrary, the machine can continue operating without any intervention. The good point about predictive maintenance is the capability of telling when a maintenance is required and when is no necessarily required which is ideal to save costs.
Answer:crane and engine I guess
Explanation:
The statement which best characterizes the relationship between a general contractor and a construction manager is that; A construction manager subcontracts a general contractor to perform <em>work</em>.
A construction project manager is saddled with the responsibility of overseeing the planning and delivery of construction projects.
- In essence, they ensure that work is completed on time and within budget. Other functions include organising logistics, delegation of work and tracking of spending.
A general contractor otherwise known as the prime contractor is responsible for the day-to-day oversight of a construction site,<em> employment of labour, management of vendors and trades, and most importantly, the communication of information to all involved parties throughout the course of a building project.</em>
- <em>Ultimately</em><em>,</em><em> </em><em>the </em><em>relationship</em><em> </em><em>between</em><em> </em><em>a </em><em>general contractor and a construction manager is that; A construction manager subcontracts a general contractor to perform work.</em>
<em>Read </em><em>more</em><em>:</em>
<em>brainly.com/question/17157892</em>
the required documents is 3000