Answer:
NPV =$ 60,311.80
Explanation:
<em>The net present value (NPV) of a project is the present value of cash inflow less the present value of cash outflow of the project.</em>
NPV = PV of cash inflow - PV of cash outflow
We can set out the cash flows of the project using the table below:
0 1 2 3
Operating cash flow 136,000 136,000 136,000
Initial cost (274,000)
Working capital (61,000 ) 61,000
Salvage value <u> </u> <u> </u> <u> </u> 1<u>5000 </u>
Net cashflow <u> (335,000) 136,000 136,000 212,000.</u>
PV inflow= (136000)× (1.1)^(-1) + (136,000× (1.1)^(-2) + (112,000)× (1.1)^(-3)
= 395,311.80
NPV =395,311.80 -335,000
=$ 60,311.80
Answer: Costs of items used up this period but paid for next period
Explanation:
Period Expenses for the period are transactions that should be expensed because they were used in the current period.
Therefore if a period cost is not used in the period, it is not considered a period cost even if the company pays for it in the current period which also means that if a period cost for the period is not paid in the current period but in the next one, it is still a period cost for the current period.
From the above therefore, the period cost is the cost of items used up in this period but paid for in the next one.
The land purchased might look like the obvious choice but it is not because Assets are capitalised and not expensed.
Answer:
The correct answer is letter "D": control.
Explanation:
The control phase of the marketing planning process involves comparing the activities that the advertising team has developed with the expected set of actions established. This phase is important to identify if the firm as a whole is meeting the desired performance or if there are adjustments necessary to be made.
Answer:
$104,000
Explanation:
The computation is shown below:
= Bribe cost per each housing inspector × number of weeks in a year × number of newly built structures each week
= $1,000 × 52 weeks × 2
= $104,000
We simply multiply the three components i.e Bribe cost per each housing inspector, number of weeks in a year, and the number of newly built structures each week so that the accurate value can come.