Answer:
e. design programming
Explanation:
The planning techniques are responsible for structuring the tasks to be performed within the project, defining the duration and the order of execution of the same, while the programming techniques try to organize the activities so that the logical temporal relationships between them, determining the calendar or the moments of time in which each one must be realized. The programming must be consistent with the objectives pursued and respect existing restrictions (resources, costs, workloads).
The programming therefore consists in setting, in an approximate way, the moments of beginning and termination of each activity. Some activities may have slack and others are critical activities (fixed over time).
STEPS:
Build a time diagram (moments of beginning and slack of activities).
Establish the times of each activity.
Analyze project costs and adjust clearances (minimum cost project).
Answer:
It will always have a zero acceleration
Answer:
not work.
Explanation:
if u are saying in a series circuit...
if 1 build burns out and theres other bulbs the circuit wont work anymore.
Answer:
force of the breaks is 6650 N, direction opposite to direction of movement
Explanation:
Answer:
E) 800 km/h
Explanation:
The computation of the average vector velocity module of the plane, at that time is shown below:
The displacement vector is
d^2 = d1^2 + d2^2
where,
d1 = northeast displacement
d2 = southeast displacement
Now
d^2 = (120)^2 + (160)^2
= 14400 + 2560
= 40000
= √40000
d = 200 km
Now the average velocity is
V = ΔS ÷ Δt
= 200 ÷ 1 ÷ 4
= 200 × 4
= 800 km/h