Answer: The engineering design process emphasizes open-ended problem solving and encourages students to learn from failure. This process nurtures students abilities to create innovative solutions to challenges in any subject! In addition to their involvement in design and development, many engineers work in testing, production, or maintenance. These engineers supervise production in factories, determine the causes of a component's failure, and test manufactured products to maintain quality.
Explanation:
Answer:
Absolute viscosity is the evaluation of the resistance (INTERNAL) of the fluid flow
Kinematic viscosity relates to the dynamic viscosity and density proportion.
SUS stands for Sabolt Universal Seconds. it is units which described the variation of oil viscosity
Explanation:
Absolute viscosity is the evaluation of the resistance (INTERNAL) of the fluid flow, whereas Kinematic viscosity relates to the dynamic viscosity and density proportion. fluid with distinct kinematic viscosities may have similar dynamic viscosities and vice versa.Dynamic viscosity provides you details of power required to make the fluid flow at some rate, however kinematic viscosity shows how quick the fluid moves when applying a certain force.
SUS stands for Sabolt Universal Seconds. it is units which described the variation of oil viscosity when change with change in temperature. it is measured by using viscosimeter.
Answer:
The solution for the given problem is done below.
Explanation:
M1 = 2.0
= 0.3636
= 0.5289
= 0.7934
Isentropic Flow Chart: M1 = 2.0 ,
= 1.8
T1 =
(1.8)(288K) = 653.4 K.
In order to choke the flow at the exit (M2=1), the above T0* must be stagnation temperature at the exit.
At the inlet,
T02=
= (1.8)(288K) = 518.4 K.
Q= Cp(T02-T01) =
= 135.7*
J/Kg.
Answer:
Time =t2=58.4 h
Explanation:
Since temperature is the same hence using condition
x^2/Dt=constant
where t is the time as temperature so D also remains constant
hence
x^2/t=constant
2.3^2/11=5.3^2/t2
time=t^2=58.4 h
The answer is choice C
Explanation:
As during construction ,the site is cleared for all debris before laying out the foundation. Even the sewer lines are dug out .
So it will be useful for the construction crews to connect the pipes to the sewer lines before the foundation is poured.
But usually the steps take in construction activity is:- first the site is cleared for the foundation to be poured and once the foundation wall is set , then all utilities , including plumbing and electrical activities are done.,
After this process is over, the city inspector comes to check whether the foundation has been laid down as per the code of construction.
Only after that the rest of the construction activity follows through.