Answer: (a) +/- 7.5° (b) +/- 3.75°
Explanation:
See attachment
Answer:
Given that
Mass flow rate ,m=2.3 kg/s
T₁=450 K
P₁=350 KPa
C₁=3 m/s
T₂=300 K
C₂=460 m/s
Cp=1.011 KJ/kg.k
For ideal gas
P V = m R T
P = ρ RT


ρ₁=2.71 kg/m³
mass flow rate
m= ρ₁A₁C₁
2.3 = 2.71 x A₁ x 3
A₁=0.28 m²
Now from first law for open system

For ideal gas
Δh = CpΔT
by putting the values


Q= - 45.49 KJ/kg
Q =- m x 45.49 KW
Q= - 104.67 KW
Negative sign indicates that heat transfer from air to surrounding
Answer:
total amount of water after 2 min will be 84.4 kg/s
Explanation:
Given data:
one tank inflow = 0.1 kg/s
2nd tank inflow = 0.3 kg/s
3rd tank outflow = 0.03 kg/s
Total net inflow in tank is = 0.3 +0.1 =0.4 kg/s
From third point, outflow is 0.03 kg/s
Therefore, resultant in- flow = 0.4 - 0.03
Resultant inflow is = 0.37 kg/s
Tank has initially 40 kg water
In 2 min ( 2*60 sec), total inflow in tank is 0.37*60*2 = 44.4 kg
So, total amount of water after 2 min will be = 40+44.4 = 84.4 kg
Answer:
Explanation:
This will be possible when setting them up in summer with a certain quantity of sag, they have already know that the cables won't be able to sag any further because of the heat. During winter, when the cables contract because of the cold weather, the sag will therefore be reduced, but much tension will not be put on the cables.
Answer:
peak flow and any engineering considerations related thereto
Explanation:
It should be no surprise that a peak flow meter will report peak flow, sometimes with important maximum-value, time-constant, or bandwidth limitations. There are many engineering issues related to flow rates. A peak flow meter can allow you to assess those issues with respect to the flows actually encountered.
Peak flow can allow you to assess adequacy of flow and whether there may be blockages or impediments to flow that reduce peak levels below expected values. An appropriate peak flow meter can help you assess the length of time that peak flow can be maintained, and whether that delivers sufficient volume.
It can also allow you to assess whether appropriate accommodation is made for unexpectedly high flow rates. (Are buffers or overflow tanks of sufficient size? Is there adequate protection against possible erosion? Is there adequate support where flow changes direction?)